These first shots are of the front approach to the house. Once the steel I-beam was delivered and installed, the remaining portion of the roof and overhang were completed. We were very happy with how this piece of the project turned out.
The plumber has been roughing-in all of the fixtures. We are looking forward to putting that tub to use.
Once the electrician and plumber were done, the cement contractor was able to pour the cement floor for the lower level. The floor turned out great! The joint lines appear to be working--no other visible cracks yet. We have an idea who was in charge of the pour...
With the cement floors poured, Tim and Co. started framing the lower level:
Last but not least, the windows are on the way. When they arrive, this should set off a flurry of activity. Looking forward to it!